Basement Underpinning & the Party Wall etc. Act 1996: A Detailed Overview
Basement underpinning is a structural technique used to strengthen and stabilize the foundation of an existing building, often to:
Create a new basement or increase the depth of an existing one.
Support a weakened foundation due to soil movement, subsidence, or construction defects.
Allow for load-bearing improvements, such as the addition of floors above.
Underpinning is often required in urban residential settings, especially in older buildings that were not originally designed to support a basement or additional loads. At Party Wall Expert we specialise in Basement excavation, underpinning and conversions having completed over 1,000 devlopments involving the Party Wall etc. Act 1996.
Mass Concrete Underpinning (Traditional Method):
Small sections of soil beneath the foundation are excavated and filled with concrete in a sequenced manner.
This gradually transfers the building load to a deeper, more stable level.
Mini-Piled Underpinning:
Used where ground conditions are poor or where deep excavations are required.
Small-diameter piles are drilled and installed, often reaching 5–15 meters deep.
Beam and Base Underpinning:
Reinforced concrete beams replace part of the original foundation.
These beams distribute the load to mass concrete bases installed beneath.
Box or Basement Underpinning:
Often used in full basement conversions.
A reinforced concrete box is constructed beneath the building, replacing or supplementing the original foundation.
The Party Wall etc. Act 1996 is UK legislation that provides a framework for preventing and resolving disputes related to party walls, boundary walls, and excavations near neighbouring buildings.
Party Wall: A wall shared by two properties, typically between semi-detached or terraced houses.
Adjoining Owner: The owner of the property next door.
Building Owner: The person intending to carry out works covered by the Act.
Basement underpinning almost always triggers the Act because of the following provisions:
Section 1 – Line of Junction Works:
Applies if you plan to build a new wall at or astride the boundary line.
Section 2 – Works to a Party Wall:
Covers work to a party wall or structure, such as cutting into it to insert beams or underpinning it.
Also includes raising, thickening, or demolishing a party wall.
Section 6 – Adjacent Excavation and Construction:
Applies when excavating within:
3 metres of a neighbouring structure and to a depth deeper than its foundations.
6 metres, depending on the angle and depth of excavation compared to the neighbour's foundation.
Because basement underpinning involves deep excavation and structural work close to (or on) a party wall, Sections 2 and 6 are typically both invoked.
The Building Owner must serve formal written notices to the Adjoining Owner(s), typically:
At least 1 month before excavation (under Section 6).
At least 2 months before work affecting a party wall (under Section 2).
If the Adjoining Owner consents, work may proceed with conditions agreed informally. However, if they dissent or do not reply within 14 days, a Party Wall Award must be prepared.
Scope and description of the work.
Schedule of condition of adjoining properties (with photos).
Access rights and working hours.
Protective measures (e.g., vibration monitoring, crack gauges).
Insurance or security for expenses provisions.
Surveyors may be appointed:
One Agreed Surveyor, or
One for each party (two-surveyor model), with a Third Surveyor to resolve disputes.
Basement works can cause significant issues if not properly managed:
Subsidence or structural movement in neighbouring buildings.
Water ingress, especially in areas with high water tables.
Disputes and legal claims under common law or under the Act.
Therefore, compliance with the Party Wall Act is both a legal requirement and a risk management measure.
The Act does not give planning permission or Building Regulations approval — both must be obtained separately.
Non-compliance can lead to:
Injunctions to stop work.
Claims for damages due to negligence or trespass.
Delays and additional costs from legal proceedings.
Basement underpinning is a complex engineering process requiring significant technical planning and legal compliance. The Party Wall etc. Act 1996 plays a critical role in ensuring that adjoining owners are protected, disputes are managed fairly, and works proceed in a structured manner. Early engagement with a party wall surveyor, structural engineer, and legal counsel (if needed) is strongly advised before starting underpinning work.
To obtain a quotation Click Here